LAWA  
LAWA     LAX     ONT     VNY     HOME  
       
 
  stakeholder liaison  
  specific plan amendment study  
  projects - publications  
  lax master plan program  
  overview  
  about the program  
  LAX master plan stipulated settlement  
  community benefits agreement  
  publications  
  South Airfield Improvement Project  
    Final EIR  
    Draft EIR  
    Notice of Completion  
    SAIP Fact Sheet  
    Public Workshop Exhibits August 10th  
    Public Meetings  
    Welcome Sheet  
    Presentation  
    Project Overview  
    SAIP FAQs - English  
    SAIP FAQs - Spanish  
  Crossfield Taxiway Project  
  LAX traffic alerts  
  technical studies - north airfield  
 
 
 
South Airfield Construction>Construction Notices
 
 

 
April 2, 2007 – Construction of Runway 25L complete. The runway was re-opened for traffic shortly after noon and American Airlines flight number 1247 from Chicago was the first to land on the new runway.

April 9, 2007 – Construction of the new Center Taxiway begins and is expected to be complete in June 2008. Construction will require closures of Runway 25R to complete connection of the new taxiway to Runway 25R. These closures will occur on weekends from 2:00 AM on Saturday until 6:00 AM on Monday. Closures are scheduled to begin in June 2007 and end in April 2008.

June 22, 2007 – Weekend closures of Runway 25R will start on June 23, 2007.

 
     
 

 